Pick your project and your start date. We'll turn real lead times into an order-by date for every item — so nothing puts your project on hold. Free, no sign-up.

11 of 38 items need to be ordered before work starts — and 2 are already past their order-by date for this start date.

📬 Email me this plan, and remind me when each order is due

You get these order-by dates in your inbox now, then one short reminder in the week each item needs ordering. Nothing else, and you can unsubscribe any time.

Rough-In and Framing

phase starts Jan 23, 2027

  • Windowsorder by Oct 25, 2026 · order now
  • Cement board (behind backsplash)order by Jan 9, 2027

Insulation, Drywall, and Paint

phase starts Jan 31, 2027

  • Insulationorder by Jan 17, 2027
  • Drywall / drywall repairsorder by Jan 17, 2027
  • Wall paintorder by Jan 29, 2027
  • Ceiling paintorder by Jan 29, 2027
  • Trim paintorder by Jan 29, 2027
  • Caulk / touch-up paintorder by Jan 29, 2027

Flooring

phase starts Feb 9, 2027

  • Flooringorder by Jan 10, 2027
  • Grout (if using tile)order by Feb 4, 2027

Cabinetry

phase starts Feb 13, 2027

  • Cabinets (uppers + lowers)order by Oct 16, 2026 · order now
  • Drawer slidesorder by Jan 30, 2027
  • Cabinet pulls & knobsorder by Jan 30, 2027
  • Doors (interior)order by Jan 30, 2027
  • Trim / crown moldingorder by Jan 30, 2027
  • Door hardware / knobs / leversorder by Jan 30, 2027
  • Under-cabinet lighting (mount channels)order by Jan 30, 2027
  • Recessed ceiling lightsorder by Jan 30, 2027
  • Island pendantsorder by Jan 30, 2027
  • Switches & GFCI outletsorder by Jan 30, 2027
  • Outlet covers / switch platesorder by Feb 8, 2027

Countertops and Backsplash

phase starts Feb 19, 2027

  • Countertoporder by Dec 21, 2026
  • Backsplash tileorder by Jan 20, 2027

Fixtures and Appliance Installation

phase starts Mar 1, 2027

  • Rangeorder by Dec 1, 2026
  • Wall ovenorder by Dec 1, 2026
  • Cooktoporder by Dec 1, 2026
  • Refrigeratororder by Dec 1, 2026
  • Kitchen sinkorder by Feb 15, 2027
  • Kitchen faucetorder by Feb 15, 2027
  • Prep/bar sinkorder by Feb 15, 2027
  • Pot fillerorder by Feb 15, 2027
  • Garbage disposalorder by Feb 15, 2027
  • Range hood / ventilationorder by Feb 15, 2027
  • Microwaveorder by Feb 15, 2027
  • Dishwasherorder by Feb 15, 2027
  • Under-cabinet lighting (final hookup)order by Feb 15, 2027
  • Sink task lightorder by Feb 15, 2027
  • Window treatments / blinds / shades / curtainsorder by Feb 15, 2027

Dates change. Your plan should change with them.

Save this plan as a free Hausbound project: check items off as you order, forward order emails to auto-track deliveries, and every order-by date recomputes when your schedule moves.

Save my plan — freeor get the app on your phone

Know someone else mid-renovation? Send them this plan — it opens the same free tool with these dates already filled in.

Planning a basement, laundry room, home office, or another project? Those templates — with the same order-by engine — are included with Hausbound's unlocked plans.

How this works

Your start date sets when each build phase begins, and every item's order-by date is worked backward from the phase that needs it, using conservative lead times — the full method is in the renovation ordering timeline.

What's different here: these are one-time estimates, but inside Hausbound the same engine recomputes your dates automatically when your schedule moves, your retailer quotes a different lead time, or an order email lands in your Hausbound Mailbox.