Budget & money

Change orders: what they cost, how to price one, and how to keep them from eating the contingency

A change order is a written, signed agreement to change the scope, price or schedule of the job, made before the changed work starts. It usually costs the contractor's actual cost for labor and materials plus a markup, commonly 10 to 20 percent for overhead and profit (some contracts set the figure, so check yours), and it should state the number of schedule days it adds or removes. Handled well, a change order is just a price you saw first. Handled badly, it is a text message, a handshake and a surprise at final payment. Below: what goes on one, how to check the price, and how to keep them inside your contingency.

November 22, 2026 · 6 min read

What a change order has to say

Whatever the form looks like, a usable one has five lines. If any is blank, the change is not agreed yet.

LineWhat it should sayWhy it matters
What changedOne or two plain sentences, with the room and the product or measurementWithout it, nobody remembers later what was approved
PriceAdded cost or credit, with labor and materials separate, and the markup shownLets you check the math and compare against the contract's rate
Schedule daysCalendar or working days added, or 'none'A blank here usually means the contractor assumed none and will find some later
Revised contract totalOld total, this change, new totalKeeps a running number so five small changes do not hide
Signatures and dateBoth parties, before the work startsAn unsigned change order is an argument waiting to happen

How a change order is priced

The usual formula is direct cost (materials, the subcontractor's price or the crew's labor hours) plus a markup for overhead and profit. Markups of 10 to 20 percent are common, and some contractors charge the same percentage they built into the original bid. Your contract may fix the percentage, so look there first. If it does not, ask what they charge and whether it is the same on credits. A change that removes work should come back to you at cost, or with the markup, not at a discount that quietly disappears.

ExampleDirect costMarkup at 15%Change order price
Add two recessed lights$300$45$345
Upgrade to a larger tile$1,200$180$1,380
Move a plumbing supply line$900$135$1,035
Add a pocket door in place of a swing door$2,400$360$2,760

These figures are illustrations of the arithmetic, not quotes. Real costs depend on your market, the trade and what is behind the wall. Ask for the direct-cost breakdown on anything over a few hundred dollars. A fair contractor expects the question.

Markup applies once. If a subcontractor already marked up their price and the general contractor marks that up again, that is normal and usually fair, but the total should still be a number you agreed to in writing. What you should not see is markup on markup on an allowance overage that your contract already priced.

The schedule days are the hidden cost

A change that costs $345 can still cost a week, if it touches something with a lead time or a trade who has already left the job. A change order should always carry a schedule line, even if it reads "0 days". Things that turn a small change into delay:

  • Anything that needs a new inspection or permit revision. Adding circuits or moving a plumbing line can change what the inspector reviews. See do you need a permit to remodel.
  • Anything ordered. A different cabinet, tile or fixture restarts the lead time, and the order must be placed before the rest of the schedule moves.
  • Anything after the walls are closed. The same change costs more once it means opening drywall and patching it. That is the reason to decide the rough-in items early.
  • Anything that sends a trade back. A tradesperson recalled for one hour often charges a minimum trip, and may not be able to return for a week or more. The timeline effect on a whole job is in how long a kitchen remodel takes.

How to keep change orders from eating the contingency

A contingency of 10 to 20 percent of the budget exists for surprises: rot behind a wall, wiring that is not to code, a subfloor that needs leveling. Your own changes of mind do not belong in it. Money for those should come from a line you control. The setup is in how much renovation contingency to hold.

  • Keep two buckets. One for problems found (contingency) and one for choices you change (a small upgrade fund, even 3 to 5 percent). When the second is empty, the next change is a conversation, not an assumption.
  • Write the rule into the contract. No work outside the original scope without a signed change order, and no payment requested for work that is not on one. Most form contracts already say this; ask whether yours does.
  • Sign before the work. A verbal "go ahead" in the hallway is the single most common source of final-payment disputes. If time matters, a message that both sides confirm with the price in it is better than nothing, and the formal paper follows within a day or two.
  • Batch the small ones. Each change order has paperwork and, often, a minimum charge. Collect questions during a weekly walk-through and decide them together.
  • Track the running total. Keep the contract total, every signed change and the amount of contingency used in one place, and look at it before approving the next.

When to push back

Not every extra is a change order. A fair test is whether the work was reasonably part of what was bid. If your contract said "install owner-supplied tile" and the contractor now says the subfloor must be flattened first, ask whether the bid assumed a flat floor and what the inspection found. If the cause was an error in the plans or the bid, the conversation is different from a change you requested. Ask in writing, calmly, and ask for the breakdown.

Unresolved changes should also be settled before the last payment, because the final check is where leverage is. How to hold that payment fairly is in the punch list and final payment. Deposit limits, lien rights and written-contract requirements vary by state, so check your state's rules or a local attorney before relying on any figure here.